x__32__fill__social media twitter voice record__64__outline__user profile avatar contact person volume sound users member human speaker record voice recorder speach speak apartment__64__fill__building home house hotel apartment property flat residence

Project timeline

A full timeline will be available after several key phases involved in setting up the project – including the appointment of contractors – have been completed.

June 2025
  • Evaluation of pricing completed.
March 2025
  • Design submitted for council approval of tender process
  • Building consent issued.
July to October 2024
  • Contractor appointed for demolition
  • Demolition begins (mid July)
  • Demolition ends (September)
  • Concept design signed off
  • Costings plan and full project timeline completed
  • Resource consent and building consent process begins.
June 2024
  • Tenders close for the contract to demolish the buildings on the site where the new library will be located.
May 2024
  • Design brief confirmed
  • Design team appointed
  • Draft design process is expected to take five months.

Last updated: 03 Jul 2025 9:51am