x__32__fill__social media twitter voice record__64__outline__user profile avatar contact person volume sound users member human speaker record voice recorder speach speak apartment__64__fill__building home house hotel apartment property flat residence

Fluoridation project enters key construction phase

Construction is now underway on the Far North’s water fluoridation programme, with work progressing to meet a Ministry of Health deadline of 31 July 2026.

The project will introduce fluoride dosing systems into the Kerikeri and Kaitaia town water supplies, with both sites tracking toward installation and commissioning over the coming months.

In July 2023, the Director-General of Health directed the Far North District Council under section 116E the Health Act to fluoridate drinking water for Kaitāia and Kerikeri. FNDC is one of 14 local authorities directed to fluoridate water supplies. In accordance with the Act, the council is required to ensure the Kerikeri and Kaitāia water supplies are fluoridated at optimal levels. The council is required by law to comply with the ministry’s directive. If the council doesn’t comply, it faces a fine of up to $100,000.00 per non-compliant site and $10,000.00 per day per site until compliance is achieved.

The project to introduce fluoridation is split into two components. Package A covers the fluoridation equipment, with the ProSaT-5 unit supplied by Prominent NZ selected as the Ministry of Health-approved solution. The system uses a powder-based dosing process designed to be safe for operators and straightforward to manage, supporting reliable day-to-day operation once installed.

Package B includes the civil construction, building works, pipe connections and electrical integration required to support the dosing system. This package has been directly awarded to contractor Bellcon, which is responsible for preparing each site so the ProSaT-5 units can be installed and connected.

At Kerikeri, foundation work is currently underway, with the base course already laid and steel installation and boxing in progress. The building is scheduled to be delivered to site on 18 May. In Kaitaia, work is pending the removal of the existing UV unit, after which the new building will be delivered and positioned, with this stage currently booked for 29 May.

Installation of the fluoride dosing equipment is scheduled to begin on 1 June 2026 and is expected to take approximately one month.

A further one-month allowance has been built into the programme for commissioning, testing and resolving any early operational issues, ensuring the system is fully optimised before going live.

You can read more background on fluoridation on council water supplies here.


Tags: News story