Project background
This large new complex provides facilities for a range of sports from around the Bay of Islands. It addresses the shortage of facilities in the region, support growing participation in sports and help meet future demand in Northland, as one of the fastest growing regions in the country.
Te Puāwaitanga - Bay of Islands Sports Hub opened in May 2025.

Project construction
Te Puāwaitanga - Bay of Islands Sports Hub project was separated into two key development phases - Phase 1 - funded and Phase 2 - unfunded.
The council worked with the project working group when preparing the resource consent application. The project working group includes iwi, sporting code representatives, elected members and council staff.
The sports hub was named Te Puāwaitanga, which means a home of belonging, play and growth.
Phase 1 - funded was completed in April and the sports fields opened in May 2025. Phase 1 of the sports hub construction had a budget of $10.758 million, with $8.758 million provided by council and $2 million from the government’s COVID-19 Response and Recovery Fund.
Phase 2 - unfunded focuses on future development options. The existing resource consent considers future options and what is needed to support the growth of sports in the region.
Further engagement is required to confirm the priorities and timings needed in order to achieve this. The works will then be undertaken as funding becomes available.
Activity | Detail | Month/Year |
|---|---|---|
Overall concept design development | Overall layout Building concept Access provision | October 2020 - July 2021 |
| Stakeholder engagement | Project working group Direct neighbour engagement | October 2020 – July 2021 |
Site access and utility connections | Access from SH10 Utilities connections; fibre optic and power feeds Shelter belt tree removal – western edge | April 2021-October 2021 |
Public engagement on overall concepts | Drop-in sessions for affected stakeholders and interested public | Mid-Late July 2021 |
Consenting | Resource consent applications lodged for on-site developments | Late 2021 |
Consent processing and submissions | Public submissions opportunity on sports hub proposals | From early 2022 |
Approvals | Review and approvals with FNDC and NRC | Early to mid 2022 |
Phase One construction | Vegetation removal Construction of four fields New ablution block and changing rooms (if budget allows) Storm water and used water facility | Late 2022 |
Phase One construction | Remaining onsite developments for Phase One | 2023 to May 2025 |
| Phase One construction ends | Construction finishes in April 2025 | April 2025 |
| Te Puāwaitanga - Bay of Islands Sports Hub opens | Te Puāwaitanga opens in May 2025, catering for multiple activities | May 2025 onwards |