Infrastructure Planned Procurements

Find out what infrastructure capital works procurements council is planning for the rest of the 2024 to 2027 Long Term Plan period. The Forward Programme of Planned Infrastructure Capital Works Procurements gives suppliers, contractors and the community an early look at upcoming work. It is intended to help with planning, and project details and timings may change.

PORTFOLIODescription of WorksCurrent Project StageConstruction Value RangeEstimated Procurement MethodEstimated Tender Release + Financial YearTender Status
STORMWATER
      
Kaitāia - Commerce St S/W RenewalRenewal of S/W reticulation on West Lane bounded between Taaffe St, Bank St and Puckey AveTender$500k - $1mOpenJan - Mar (2025/2026, Q3)Awarded
Kaitāia - Parkdale Cres Stormwater Culvert RenewalUrgent renewal of 250m long 1200mm dia concrete culvertTender$500k - $1mOpenApr-June (2025/2026, Q4)To Market
Kaitāia - Matthews Ave to Farrimond PlaceRenewal and diversion of S/W pipes conveying flow from Matthews Ave to Farrimond PlaceDesign$500k - $1mOpenOct-Dec (2026/2027, Q2)Planned
Kaitāia - Lake Rd Pipe RenewalReticulation UpgradesFeasibility$50k - $500kOpenJan - Mar (2026/2027, Q3)Planned
Ahipara - Tasman HeightsRenewal and upgrade of S/W system serving Tasman HeightsDesign$50k - $500kOpenOct-Dec (2026/2027, Q2)Planned
Ahipara - Reef View Rd Stormwater UpgradesVarious works to drains, watercourse inlet, culvert to resolve flood conveyance and damageDesign$500k - $1mOpenOct-Dec (2026/2027, Q2)Planned
Mabel Thorburn Pl, Mangōnui Stormwater UpgradesVarious works to open drains, inlets/outlets, culvert to resolve flood conveyance and damageDesign$500k - $1mOpenOct-Dec (2026/2027, Q2)Planned
Moerewa - Stormwater Improvements Stage 2Continuation of reticulation upgrades.Feasibility$1m - $2mOpenOct-Dec (2026/2027, Q2)Planned
Kaitāia - Stormwater Floodgate ImprovementsUpgrades to existing floodgatesDesign$50k - $500kDirectApr-June (2025/2026, Q4)Awarded
Kaikohe - Network Gross Debris Trap UpgradesReplacement of Gross Pollution Traps - Improvements to performance and safetyDesign$50k - $500kDirectJul-Sept (2026/2027, Q1)Planned
Kaikohe - Network Improvements Station RdReticulation UpgradesFeasibility$50k - $500kOpenOct-Dec (2026/2027, Q2)Planned
Kawakawa - 22 Commercial St Pipe RenewalReticulation UpgradesFeasibility$1m - $2mOpenJan - Mar (2026/2027, Q3)Planned
Kawakawa - Network Catchpit ImprovementsReticulation UpgradesFeasibility$50k - $500kOpenOct-Dec (2026/2027, Q2)Planned
Kawakawa - 25 Gillies St Inlet Structure UpgradeReticulation UpgradesFeasibility$500k - $1mOpenJan - Mar (2026/2027, Q3)Planned
Kerikeri - 61 Cobham Rd Extension UpgradesReticulation UpgradesFeasibility$50k - $500kOpenJan - Mar (2026/2027, Q3)Planned
Paihia - Zonal MonitoringInstallation of zonal monitoring equipment to facilitate targeted leak detection.Design$50k - $500kDirectJul-Sept (2026/2027, Q1)Planned

PORTFOLIODescription of WorksCurrent Project StageConstruction Value RangeEstimated Procurement MethodEstimated Tender Release + Financial YearTender Status
WASTEWATER
      
District Wide - SCADA Telemetry and System UpgradesMulti-Year Project of upgrades across the district WWTP/WTP's - Ongoing procurements as work progresses through various stages.Design$2m - $5mOpenMultiplePlanned
District Wide - Critical Spares ProgrammeProcurement of critical spare components and transferable equipmentDesign$50k - $500kDirectJul-Sept (2026/2027, Q1)Planned
District Wide - Wastewater PS Odour Devices ProgrammeInstallation of a range of tailored odour mitigation solutionsDesign$50k - $500kOpenOct-Dec (2026/2027, Q2)Planned
District Wide - Wastewater PS Renewals and UpgradesSite specific upgrade programmeDesign$2m - $5mOpenJan-Mar (2026/2027, Q3)Planned
District Wide - Wastewater Monitoring Site UpgradesImprove access and upgrade monitoring infrastructureFeasibility$1m - $2mOpenJan-Mar (2026/2027, Q3)Planned
Ōpua - Baffin St WW Pump Station Upgrades, Watermains2 x pump station upgrades, wastewater and water supply reticulation upgrades, electrical, demolish old WWTP, 470m rising main upgradeDesign$1m - $2mOpenJul-Sept (2026/2027, Q1)Planned
Kaitāia - W/W Network RenewalsRolling programme of network reticulation renewalsDesign$500k - $1mOpenJul-Sept (2026/2027, Q1)Planned
Kaitāia - WWTP Upgrades Stage 1Kaitāia WWTP Asset UpgradesDesign$5m - $10mOpenJan-Mar (2026/2027, Q3)Planned
Kaikohe - Network RenewalsReticulation UpgradesDesign$1m - $2mOpenJul-Sept (2026/2027, Q1)Planned
Kaikohe - Wastewater Scheme ImprovementsReticulation/Compliance upgrades to increase capacity to meet future demand.Feasibility$500k - $1mOpenOct-Dec (2026/2027, Q2)Planned
Kaikohe - WWTP Upgrades - (IAF)New plant, additional capacity for growthDesignOver $10mOpenOct-Dec (2026/2027, Q2)Planned
Kawakawa Water Supply Trunk Main Renewal/UpgradeProgramme of upgrades to 375mm dia trunk main from source to Moerewa ReservoirFeasibility$2m - $5mOpenJul-Sept (2026/2027, Q1)Planned
Kawakawa WWTP Upgrades (IAF)New plant, additional capacity for growthDesignOver $10mOpenOct-Dec (2026/2027, Q2)Planned
Kawakawa WW Reticulation Upgrades (IAF)Various network upgradesDesign$5m - $10mOpenOct-Dec (2026/2027, Q2)Planned
Wastewater Infiltration & Inflow ProgrammeI&I works to Russel, Paihia, Whatuwhiwhi, Opononi, and Hihi wastewater schemesFeasibility$2m - $5mOpenOct-Dec (2026/2027, Q2)Planned
Ōpononi WWTP Upgrades Stg 2Tertiary treatment upgrades to improve discharge qualityFeasibility$2m - $5mOpenJan-Mar (2026/2027, Q3)Planned
Hīhī - WWTP ReplacementNew plant to replace temporary solutionFeasibility$5m - $10mOpenJan-Mar (2026/2027, Q3)Planned
Whatuwhiwhi - WWTP UpgradesWWTP upgrades to improve discharge qualityFeasibility$2m - $5mOpenApr-Jun (2026/2027, Q4)Planned
Ngāwhā - Network ImprovementsInstallation of new macerator pumpsDesign$50k - $500kDirectJul-Sept (2026/2027, Q1)Planned
Kohukohu - WWTP ImprovementsWWTP UpgradesDesign$50k - $500kOpenJan-Mar (2026/2027, Q3)Planned
Kerikeri - Wastewater Storage Pump Capacity ImprovementsPS4 pump capacity and storage upgrade to meet growth/demand.Feasibility$50k - $500kOpenOct-Dec (2026/2027, Q2)Planned

PORTFOLIODescription of WorksCurrent Project StageConstruction Value RangeEstimated Procurement MethodEstimated Tender Release + Financial YearTender Status
WATER      
District Wide - SCADA Telemetry and System UpgradesMulti-Year Project of upgrades across the district WWTP/WTP's - Ongoing procurements as work progresses through various stages.Design$2m - $5mOpenMultiplePlanned
District Wide - Water Storage ImprovementsProvision of additional water storageFeasibility$1m - $2mOpenOct-Dec (2026/2027, Q2)Planned
Haruru - Kaipatiki Rise Watermain UpgradeReticulation UpgradesTender$500k - $1mOpenJan-Mar (2025/2026, Q3)Evaluation
Kaikohe - Retic RenewalsReticulation UpgradesDesign$2m - $5mOpenJul-Sept (2026/2027, Q1)Planned
Paihia/Haruru/Opua/Waitangi - New Water Treatment Plant to replace existingReplace old plant in flood area and provide additional capacity for growthFeasibilityOver $10mOpenOct-Dec (2026/2027, Q2)Planned
Paihia - Zonal MonitoringInstallation of monitoring equipmentDesign$500k - $1mDirectJul-Sept (2026/2027, Q1)Awarded
Paihia - Flows to Te Haumi ReservoirReticulation UpgradesFeasibility$1m - $2mOpenOct-Dec (2026/2027, Q2)Planned
Kawakawa - Retic RenewalsReticulation UpgradesDesign$2m - $5mOpenOct-Dec (2026/2027, Q2)Planned
Ōpononi - Fire Flow Upgrade Stage 1 Fairlie CresUpgrade and extend Ōpononi Water SupplyDesign$1m - $2mOpenJan-Mar (2026/2027, Q3)Planned
Morewa - Retic Renewals (Pembroke, Massey, Ranfurly and Reed)Reticulation UpgradesDesign$500k - $1mOpenOct-Dec (2026/2027, Q2)Planned
Kerikeri Water Treatment Plant UpgradeAdditional capacity for growthFeasibility$5m - $10mOpenApr-Jun (2026/2027, Q4)Planned

PORTFOLIODescription of WorksCurrent Project StageConstruction Value RangeEstimated Procurement MethodEstimated Tender Release + Financial YearTender Status
DISTRICT FACILITIES
      
Pukenui Coastal Walkway Section 2New walkway from SH1/Waterfront Drive to 3960 SH1Tender$500k - $1mOpenJan-Mar (2025/2026, Q3)Evaluation
Te Hiku Revitalisation - Puekpoto FootpathNew footpath linking Pukepoto School to Te Uri O Hina and Te Rarawa MaraeDesign$500k - $1mOpenOct-Dec (2026/2027, Q2)Planned

PORTFOLIODescription of WorksCurrent Project StageConstruction Value RangeEstimated Procurement MethodEstimated Tender Release + Financial YearTender Status
SOLID WASTE
      
Kaitāia Resource Recovery Centre - New BridgeReplacement of bridge accessing the Resource Recovery CentreDesign$500k - $1mOpenJul-Sept (2026/2027, Q1)To Market

Last updated: 19 Jun 2026 4:23pm