Infrastructure Planned Procurements
Find out what infrastructure capital works procurements council is planning for the rest of the 2024 to 2027 Long Term Plan period. The Forward Programme of Planned Infrastructure Capital Works Procurements gives suppliers, contractors and the community an early look at upcoming work. It is intended to help with planning, and project details and timings may change.
| PORTFOLIO | Description of Works | Current Project Stage | Construction Value Range | Estimated Procurement Method | Estimated Tender Release + Financial Year | Tender Status |
|---|---|---|---|---|---|---|
STORMWATER | ||||||
| Kaitāia - Commerce St S/W Renewal | Renewal of S/W reticulation on West Lane bounded between Taaffe St, Bank St and Puckey Ave | Tender | $500k - $1m | Open | Jan - Mar (2025/2026, Q3) | Awarded |
| Kaitāia - Parkdale Cres Stormwater Culvert Renewal | Urgent renewal of 250m long 1200mm dia concrete culvert | Tender | $500k - $1m | Open | Apr-June (2025/2026, Q4) | To Market |
| Kaitāia - Matthews Ave to Farrimond Place | Renewal and diversion of S/W pipes conveying flow from Matthews Ave to Farrimond Place | Design | $500k - $1m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Kaitāia - Lake Rd Pipe Renewal | Reticulation Upgrades | Feasibility | $50k - $500k | Open | Jan - Mar (2026/2027, Q3) | Planned |
| Ahipara - Tasman Heights | Renewal and upgrade of S/W system serving Tasman Heights | Design | $50k - $500k | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Ahipara - Reef View Rd Stormwater Upgrades | Various works to drains, watercourse inlet, culvert to resolve flood conveyance and damage | Design | $500k - $1m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Mabel Thorburn Pl, Mangōnui Stormwater Upgrades | Various works to open drains, inlets/outlets, culvert to resolve flood conveyance and damage | Design | $500k - $1m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Moerewa - Stormwater Improvements Stage 2 | Continuation of reticulation upgrades. | Feasibility | $1m - $2m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Kaitāia - Stormwater Floodgate Improvements | Upgrades to existing floodgates | Design | $50k - $500k | Direct | Apr-June (2025/2026, Q4) | Awarded |
| Kaikohe - Network Gross Debris Trap Upgrades | Replacement of Gross Pollution Traps - Improvements to performance and safety | Design | $50k - $500k | Direct | Jul-Sept (2026/2027, Q1) | Planned |
| Kaikohe - Network Improvements Station Rd | Reticulation Upgrades | Feasibility | $50k - $500k | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Kawakawa - 22 Commercial St Pipe Renewal | Reticulation Upgrades | Feasibility | $1m - $2m | Open | Jan - Mar (2026/2027, Q3) | Planned |
| Kawakawa - Network Catchpit Improvements | Reticulation Upgrades | Feasibility | $50k - $500k | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Kawakawa - 25 Gillies St Inlet Structure Upgrade | Reticulation Upgrades | Feasibility | $500k - $1m | Open | Jan - Mar (2026/2027, Q3) | Planned |
| Kerikeri - 61 Cobham Rd Extension Upgrades | Reticulation Upgrades | Feasibility | $50k - $500k | Open | Jan - Mar (2026/2027, Q3) | Planned |
| Paihia - Zonal Monitoring | Installation of zonal monitoring equipment to facilitate targeted leak detection. | Design | $50k - $500k | Direct | Jul-Sept (2026/2027, Q1) | Planned |
| PORTFOLIO | Description of Works | Current Project Stage | Construction Value Range | Estimated Procurement Method | Estimated Tender Release + Financial Year | Tender Status |
|---|---|---|---|---|---|---|
WASTEWATER | ||||||
| District Wide - SCADA Telemetry and System Upgrades | Multi-Year Project of upgrades across the district WWTP/WTP's - Ongoing procurements as work progresses through various stages. | Design | $2m - $5m | Open | Multiple | Planned |
| District Wide - Critical Spares Programme | Procurement of critical spare components and transferable equipment | Design | $50k - $500k | Direct | Jul-Sept (2026/2027, Q1) | Planned |
| District Wide - Wastewater PS Odour Devices Programme | Installation of a range of tailored odour mitigation solutions | Design | $50k - $500k | Open | Oct-Dec (2026/2027, Q2) | Planned |
| District Wide - Wastewater PS Renewals and Upgrades | Site specific upgrade programme | Design | $2m - $5m | Open | Jan-Mar (2026/2027, Q3) | Planned |
| District Wide - Wastewater Monitoring Site Upgrades | Improve access and upgrade monitoring infrastructure | Feasibility | $1m - $2m | Open | Jan-Mar (2026/2027, Q3) | Planned |
| Ōpua - Baffin St WW Pump Station Upgrades, Watermains | 2 x pump station upgrades, wastewater and water supply reticulation upgrades, electrical, demolish old WWTP, 470m rising main upgrade | Design | $1m - $2m | Open | Jul-Sept (2026/2027, Q1) | Planned |
| Kaitāia - W/W Network Renewals | Rolling programme of network reticulation renewals | Design | $500k - $1m | Open | Jul-Sept (2026/2027, Q1) | Planned |
| Kaitāia - WWTP Upgrades Stage 1 | Kaitāia WWTP Asset Upgrades | Design | $5m - $10m | Open | Jan-Mar (2026/2027, Q3) | Planned |
| Kaikohe - Network Renewals | Reticulation Upgrades | Design | $1m - $2m | Open | Jul-Sept (2026/2027, Q1) | Planned |
| Kaikohe - Wastewater Scheme Improvements | Reticulation/Compliance upgrades to increase capacity to meet future demand. | Feasibility | $500k - $1m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Kaikohe - WWTP Upgrades - (IAF) | New plant, additional capacity for growth | Design | Over $10m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Kawakawa Water Supply Trunk Main Renewal/Upgrade | Programme of upgrades to 375mm dia trunk main from source to Moerewa Reservoir | Feasibility | $2m - $5m | Open | Jul-Sept (2026/2027, Q1) | Planned |
| Kawakawa WWTP Upgrades (IAF) | New plant, additional capacity for growth | Design | Over $10m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Kawakawa WW Reticulation Upgrades (IAF) | Various network upgrades | Design | $5m - $10m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Wastewater Infiltration & Inflow Programme | I&I works to Russel, Paihia, Whatuwhiwhi, Opononi, and Hihi wastewater schemes | Feasibility | $2m - $5m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Ōpononi WWTP Upgrades Stg 2 | Tertiary treatment upgrades to improve discharge quality | Feasibility | $2m - $5m | Open | Jan-Mar (2026/2027, Q3) | Planned |
| Hīhī - WWTP Replacement | New plant to replace temporary solution | Feasibility | $5m - $10m | Open | Jan-Mar (2026/2027, Q3) | Planned |
| Whatuwhiwhi - WWTP Upgrades | WWTP upgrades to improve discharge quality | Feasibility | $2m - $5m | Open | Apr-Jun (2026/2027, Q4) | Planned |
| Ngāwhā - Network Improvements | Installation of new macerator pumps | Design | $50k - $500k | Direct | Jul-Sept (2026/2027, Q1) | Planned |
| Kohukohu - WWTP Improvements | WWTP Upgrades | Design | $50k - $500k | Open | Jan-Mar (2026/2027, Q3) | Planned |
| Kerikeri - Wastewater Storage Pump Capacity Improvements | PS4 pump capacity and storage upgrade to meet growth/demand. | Feasibility | $50k - $500k | Open | Oct-Dec (2026/2027, Q2) | Planned |
| PORTFOLIO | Description of Works | Current Project Stage | Construction Value Range | Estimated Procurement Method | Estimated Tender Release + Financial Year | Tender Status |
|---|---|---|---|---|---|---|
| WATER | ||||||
| District Wide - SCADA Telemetry and System Upgrades | Multi-Year Project of upgrades across the district WWTP/WTP's - Ongoing procurements as work progresses through various stages. | Design | $2m - $5m | Open | Multiple | Planned |
| District Wide - Water Storage Improvements | Provision of additional water storage | Feasibility | $1m - $2m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Haruru - Kaipatiki Rise Watermain Upgrade | Reticulation Upgrades | Tender | $500k - $1m | Open | Jan-Mar (2025/2026, Q3) | Evaluation |
| Kaikohe - Retic Renewals | Reticulation Upgrades | Design | $2m - $5m | Open | Jul-Sept (2026/2027, Q1) | Planned |
| Paihia/Haruru/Opua/Waitangi - New Water Treatment Plant to replace existing | Replace old plant in flood area and provide additional capacity for growth | Feasibility | Over $10m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Paihia - Zonal Monitoring | Installation of monitoring equipment | Design | $500k - $1m | Direct | Jul-Sept (2026/2027, Q1) | Awarded |
| Paihia - Flows to Te Haumi Reservoir | Reticulation Upgrades | Feasibility | $1m - $2m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Kawakawa - Retic Renewals | Reticulation Upgrades | Design | $2m - $5m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Ōpononi - Fire Flow Upgrade Stage 1 Fairlie Cres | Upgrade and extend Ōpononi Water Supply | Design | $1m - $2m | Open | Jan-Mar (2026/2027, Q3) | Planned |
| Morewa - Retic Renewals (Pembroke, Massey, Ranfurly and Reed) | Reticulation Upgrades | Design | $500k - $1m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| Kerikeri Water Treatment Plant Upgrade | Additional capacity for growth | Feasibility | $5m - $10m | Open | Apr-Jun (2026/2027, Q4) | Planned |
| PORTFOLIO | Description of Works | Current Project Stage | Construction Value Range | Estimated Procurement Method | Estimated Tender Release + Financial Year | Tender Status |
|---|---|---|---|---|---|---|
DISTRICT FACILITIES | ||||||
| Pukenui Coastal Walkway Section 2 | New walkway from SH1/Waterfront Drive to 3960 SH1 | Tender | $500k - $1m | Open | Jan-Mar (2025/2026, Q3) | Evaluation |
| Te Hiku Revitalisation - Puekpoto Footpath | New footpath linking Pukepoto School to Te Uri O Hina and Te Rarawa Marae | Design | $500k - $1m | Open | Oct-Dec (2026/2027, Q2) | Planned |
| PORTFOLIO | Description of Works | Current Project Stage | Construction Value Range | Estimated Procurement Method | Estimated Tender Release + Financial Year | Tender Status |
|---|---|---|---|---|---|---|
SOLID WASTE | ||||||
| Kaitāia Resource Recovery Centre - New Bridge | Replacement of bridge accessing the Resource Recovery Centre | Design | $500k - $1m | Open | Jul-Sept (2026/2027, Q1) | To Market |